Falling Sands Viaduct (Bridge 3) carries the railway across the Staffordshire & Shropshire Canal and River Stour about a mile from [[Kidderminster]].  It is built of red brick and is 132 yards in length, with seven arches of 46ft span.
+
'''Falling Sands Viaduct''' (Bridge 3) was completed in 1877 as part of the [[Kidderminster Loop Line]]. It carries the railway across the [[Staffordshire & Worcestershire Canal]] Conservation Area and 64 feet above the [[River Stour]], about a mile from [[Kidderminster]].   
  
After crossing the viaduct when travelling toward Bewdley, the area of land on the left of the line was the site of the former British Sugar Corporation's Foley Park Factory. The last visible structures on the site, two large silos, were demolished in 2012 and the area is now being developed for housing.
+
The [[Loop Line specification and contract]] of 1874 specified that the masonry of the viaduct should be "''...of the best quality of Red Sandstone of the district''". In May 1875 the contractor Charles Dickinson wrote to the GWR explaining his difficulty in obtaining suitable stone for the piers of the viaduct and requesting the difference in price for it to be built entirely of brick, to which the GWR agreed.<ref>[[Bibliography#Books|Marshall (1989)]] pp. 81-82.</ref> Accordingly the viaduct was built of red brick. It is 132 yards in length, with seven arches of 46ft span.<ref>[[Bibliography#Books|Marshall (1989)]] p. 92.</ref>
  
This area was also the site of the former [[Foley Park Halt]].  
+
The Viaduct was also numbered as Bridge 3 during the BR era; the BR-era numbering plate, which may still be seen on the northern parapet, gives its location as [[Gradient profile and mileages#Mileages|135 miles 78 chains]].
  
== See Also ==
+
==Closure==
[[Worcester Road Bridge | Towards Kidderminster]]<br>
+
===Passenger services===
[[List of infrastructure]]<br>
+
The last scheduled passenger service over the viaduct was the 19:20 DMU from Bewdley to Kidderminster on Saturday 3 January 1970, with passenger services between being formally withdrawn from 5 January 1970.<ref>[[Bibliography#Books|Marshall (1989)]] p. 164.</ref> When the SVR acquired the southern section of the line between [[Alveley Sidings]] and [[Foley Park]], the Viaduct remained in the section of the line still owned by BR. Following the SVR's reopening of Bewdley in 1974, BR ran a number of summer weekend DMU specials between their Kidderminster station and Bewdley. One of these was photographed on the Viaduct on 11 September 1982 during that year’s Enthusiasts Weekend.<ref>SVR News 66,67</ref> The last passengers to cross the Viaduct under BR ownership were on the “Severn Valley Enterprise” rail tour from Bewdley to Paddington and back on 8 October 1983.
[[Underbridge off Lisle Avenue | Towards Bridgnorth]]
+
 
 +
===Freight services===
 +
After crossing the viaduct when travelling toward Bewdley, the area of land on the left of the line was the site of the former British Sugar Corporation's Foley Park Factory.  Freight services between the factory and Kidderminster continued after 1970, finally ending with the factory’s closure in late 1982.<ref>[http://www.miac.org.uk/sugar.html Railways in Worcestershire] (retrieved  23 April 2018)</ref> The last visible structures on the site, two large silos, were demolished in 2012 and the area is now being developed for housing.
 +
 
 +
==Preservation==
 +
The line between Foley Park and Kidderminster, including the viaduct, was acquired from BR in 1984, with passenger services commencing on 30 July 1984.
 +
 
 +
===Repairs===
 +
The all-brick construction of the viaduct meant that historically it had required relatively little structural maintenance when compared with the sandstone viaducts at [[Wribbenhall Viaduct|Wribbenhall]] and elsewhere. However by around 2015 it had been determined that extensive repairs were needed to secure the Viaduct. Water had seeped into the structure causing cracks and erosion, and a speed restriction became necessary.
 +
 
 +
===2016 HLF bid rejected===
 +
On 6 September 2016 the HLF rejected a bid from the [[Severn Valley Railway Charitable Trust Ltd]] for £902,200 but "agreed the project as a medium priority for support" and "noted that a strengthened resubmission that addressed [its] concerns would be welcomed." The concerns were "that community engagement and interpretation plans were not sufficiently strong."<ref>Minutes - Heritage Lottery Fund: Committee for West Midlands Meeting on 6 September 2016</ref>
 +
 
 +
===2017-19 National Lottery Heritage Fund bid===
 +
In June 2017 the Trust secured £71,800 of HLF financial backing to develop a bid seeking £927,000 from the HLF for a large part of the quoted £1.324 million total project cost. The SVR met the challenge of raising matched funding of £397,000 (originally £275,000) for which the Trust co-ordinated efforts through a campaign entitled "'''Helping hands for Falling Sands'''". Preliminary structural investigations in Summer 2018 had revealed two gas mains, one live, which increased the cost and SVR's contribution.
 +
 
 +
The Trust submitted its bid on 26 October 2018 and on 25 March 2019 announced the award of a further £853,800 grant from The [[:Category:Lottery funding#National_Lottery_Heritage_Fund|National Lottery Heritage Fund]] which together with the earlier grant took the total amount of its funding to £925,600. The grant, along with other funds raised, was used to restore the Viaduct and to launch a programme of community engagement and exhibitions that explore the Railway’s early history. In August 2019 the Trust unveiled a large donation wall at [[The Engine House]] acknowledging the individuals, organisations and businesses who had donated to the "Helping Hands for Falling Sands" appeal, and in 2020 an exhibition was held there. [[LMS 2886 Six-wheel Passenger Brake (later 32919)|LMS six-wheel Passenger Brake 2886]] was adapted to host a mobile exhibition.
 +
 
 +
===2019-20 repair work===
 +
The timing was chosen to make the most of the annual six week shutdown period, with the work to be fully completed by the autumn in two phases.<ref>[https://www.svr.co.uk/NewsItem.aspx?a=875 SVR website]</ref>. The first stage necessitated closure of the railway between Bewdley and Kidderminster from the end of [[Christmas services]] with the line reopening at Easter. Phase 2 from May 2020 would involve replacing damaged brickwork and corbelling, and repointing throughout.<ref>[http://svrtrust.org.uk/our-projects/falling-sands-viaduct.html 'Falling Sands Viaduct', Severn Valley Railway Charitable Trust website] (Retrieved 20 November 2018)</ref><ref>Shareholders' Newsletter, undated</ref><ref>SVR News 203, 204</ref><ref>[https://www.svrlive.com/epnovember18 Express Points November 2018]</ref>
 +
 
 +
Repair work began at the very end of December 2019 with the lifting of the track by a team of volunteers and paid staff. External contractors then removed the ballast and fill from the viaduct. After the infill was removed, the contractors improved the drainage channels and added a waterproof membrane, before putting everything back together. These works were essentially complete when interrupted in March by [[2020 coronavirus disease (COVID-19) pandemic|coronavirus disease (COVID-19)]], although track was not joined and signalling not yet in place.
 +
 
 +
While the railway remained closed, the contractors began work on stage 2. Easing of lockdown restrictions allowed work on stage 1 to restart in the week of 19 June, with laying of rail completed on 25 June. The following day [[BR Class 50 50035 Ark Royal]] became the first train to cross the viaduct since December while delivering S&T equipment for the new [[Ground Frames at Foley Park|Foley Park ground frame]].<ref name="bljul20">[https://www.svrlive.com/bljul20 Branch Lines, July 2020]</ref> Discovery of roosting bats held up repairs while a licence was obtained from Natural England to allow work to be carried out.<ref name="bljul20"/> Work recommenced in August,<ref>[https://www.svrlive.com/blsep20 Branch Lines newsletter, September 2020] (Retrieved 29 August 2020)</ref> and the civil engineering work was completed in mid-December with the final piece of corbelling being slotted into place. The contractors then left the site<ref name=bljan21>[https://www.svrlive.com/bljan21 Branch Lines, January 2021]</ref>.
 +
 
 +
<gallery>
 +
File:Falling Sands 2020 repairs 1.jpg | View of the  viaduct in January 2020 with the infill removed.
 +
</gallery>
 +
 
 +
== See also ==
 +
*[[Worcester Road Bridge | Towards Kidderminster]]
 +
*[[List of infrastructure]]
 +
*[[Underbridge off Lisle Avenue | Towards Bridgnorth]]
 +
*[[Severn Valley Railway Charitable Trust Ltd]]
 +
 
 +
==References==
 +
<references />
 +
 
 +
==Links==
 +
*[http://svrtrust.org.uk/ Charitable Trust website]
 +
*[https://www.svrlive.com/charitable-trust SVRLive page]
 +
*[https://www.fallingsandsviaduct.org.uk/ Falling Sands Viaduct website]
 +
 
 +
 
 +
[[Category:Lottery funding]]
 +
[[Category:Featured articles]]

Revision as of 11:26, 11 January 2021

Falling Sands Viaduct (Geograph)

Falling Sands Viaduct (Bridge 3) was completed in 1877 as part of the Kidderminster Loop Line. It carries the railway across the Staffordshire & Worcestershire Canal Conservation Area and 64 feet above the River Stour, about a mile from Kidderminster.

The Loop Line specification and contract of 1874 specified that the masonry of the viaduct should be "...of the best quality of Red Sandstone of the district". In May 1875 the contractor Charles Dickinson wrote to the GWRGreat Western Railway explaining his difficulty in obtaining suitable stone for the piers of the viaduct and requesting the difference in price for it to be built entirely of brick, to which the GWRGreat Western Railway agreed.[1] Accordingly the viaduct was built of red brick. It is 132 yards in length, with seven arches of 46ft span.[2]

The Viaduct was also numbered as Bridge 3 during the BRBritish Rail or British Railways era; the BRBritish Rail or British Railways-era numbering plate, which may still be seen on the northern parapet, gives its location as 135 miles 78 chains.

Closure

Passenger services

The last scheduled passenger service over the viaduct was the 19:20 DMUDiesel Multiple Unit from Bewdley to Kidderminster on Saturday 3 January 1970, with passenger services between being formally withdrawn from 5 January 1970.[3] When the SVRSevern Valley Railway acquired the southern section of the line between Alveley Sidings and Foley Park, the Viaduct remained in the section of the line still owned by BRBritish Rail or British Railways. Following the SVRSevern Valley Railway's reopening of Bewdley in 1974, BRBritish Rail or British Railways ran a number of summer weekend DMUDiesel Multiple Unit specials between their Kidderminster station and Bewdley. One of these was photographed on the Viaduct on 11 September 1982 during that year’s Enthusiasts Weekend.[4] The last passengers to cross the Viaduct under BRBritish Rail or British Railways ownership were on the “Severn Valley Enterprise” rail tour from Bewdley to Paddington and back on 8 October 1983.

Freight services

After crossing the viaduct when travelling toward Bewdley, the area of land on the left of the line was the site of the former British Sugar Corporation's Foley Park Factory. Freight services between the factory and Kidderminster continued after 1970, finally ending with the factory’s closure in late 1982.[5] The last visible structures on the site, two large silos, were demolished in 2012 and the area is now being developed for housing.

Preservation

The line between Foley Park and Kidderminster, including the viaduct, was acquired from BRBritish Rail or British Railways in 1984, with passenger services commencing on 30 July 1984.

Repairs

The all-brick construction of the viaduct meant that historically it had required relatively little structural maintenance when compared with the sandstone viaducts at Wribbenhall and elsewhere. However by around 2015 it had been determined that extensive repairs were needed to secure the Viaduct. Water had seeped into the structure causing cracks and erosion, and a speed restriction became necessary.

2016 HLFHeritage Lottery Fund (National Lottery Heritage Fund from 2019) bid rejected

On 6 September 2016 the HLFHeritage Lottery Fund (National Lottery Heritage Fund from 2019) rejected a bid from the Severn Valley Railway Charitable Trust Ltd for £902,200 but "agreed the project as a medium priority for support" and "noted that a strengthened resubmission that addressed [its] concerns would be welcomed." The concerns were "that community engagement and interpretation plans were not sufficiently strong."[6]

2017-19 National Lottery Heritage Fund bid

In June 2017 the Trust secured £71,800 of HLFHeritage Lottery Fund (National Lottery Heritage Fund from 2019) financial backing to develop a bid seeking £927,000 from the HLFHeritage Lottery Fund (National Lottery Heritage Fund from 2019) for a large part of the quoted £1.324 million total project cost. The SVRSevern Valley Railway met the challenge of raising matched funding of £397,000 (originally £275,000) for which the Trust co-ordinated efforts through a campaign entitled "Helping hands for Falling Sands". Preliminary structural investigations in Summer 2018 had revealed two gas mains, one live, which increased the cost and SVRSevern Valley Railway's contribution.

The Trust submitted its bid on 26 October 2018 and on 25 March 2019 announced the award of a further £853,800 grant from The National Lottery Heritage Fund which together with the earlier grant took the total amount of its funding to £925,600. The grant, along with other funds raised, was used to restore the Viaduct and to launch a programme of community engagement and exhibitions that explore the Railway’s early history. In August 2019 the Trust unveiled a large donation wall at The Engine House acknowledging the individuals, organisations and businesses who had donated to the "Helping Hands for Falling Sands" appeal, and in 2020 an exhibition was held there. LMS six-wheel Passenger Brake 2886 was adapted to host a mobile exhibition.

2019-20 repair work

The timing was chosen to make the most of the annual six week shutdown period, with the work to be fully completed by the autumn in two phases.[7]. The first stage necessitated closure of the railway between Bewdley and Kidderminster from the end of Christmas services with the line reopening at Easter. Phase 2 from May 2020 would involve replacing damaged brickwork and corbelling, and repointing throughout.[8][9][10][11]

Repair work began at the very end of December 2019 with the lifting of the track by a team of volunteers and paid staff. External contractors then removed the ballast and fill from the viaduct. After the infill was removed, the contractors improved the drainage channels and added a waterproof membrane, before putting everything back together. These works were essentially complete when interrupted in March by coronavirus disease (COVID-19), although track was not joined and signalling not yet in place.

While the railway remained closed, the contractors began work on stage 2. Easing of lockdown restrictions allowed work on stage 1 to restart in the week of 19 June, with laying of rail completed on 25 June. The following day BR Class 50 50035 Ark Royal became the first train to cross the viaduct since December while delivering S&TSignals & Telegraph equipment for the new Foley Park ground frame.[12] Discovery of roosting bats held up repairs while a licence was obtained from Natural England to allow work to be carried out.[12] Work recommenced in August,[13] and the civil engineering work was completed in mid-December with the final piece of corbelling being slotted into place. The contractors then left the site[14].

See also

References

  1. Marshall (1989) pp. 81-82.
  2. Marshall (1989) p. 92.
  3. Marshall (1989) p. 164.
  4. SVRSevern Valley Railway News 66,67
  5. Railways in Worcestershire (retrieved 23 April 2018)
  6. Minutes - Heritage Lottery Fund: Committee for West Midlands Meeting on 6 September 2016
  7. SVR website
  8. 'Falling Sands Viaduct', Severn Valley Railway Charitable Trust website (Retrieved 20 November 2018)
  9. Shareholders' Newsletter, undated
  10. SVRSevern Valley Railway News 203, 204
  11. Express Points November 2018
  12. 12.0 12.1 Branch Lines, July 2020
  13. Branch Lines newsletter, September 2020 (Retrieved 29 August 2020)
  14. Branch Lines, January 2021

Links